1 · Conformity programmes decide when you can ship
Several African markets require conformity assessment before the goods leave China. The names differ, the logic is identical: a certificate is issued after testing or inspection in the country of origin, and without it the import file cannot be completed at destination.
Nigeria — SONCAP
A pre-shipment conformity process for regulated products, typically two to four weeks. It cannot be fixed at the port: without it the Pre-Arrival Assessment Report cannot be raised. Form M (opened through an authorised bank) and PAAR follow, but both lean on documents produced in China.
Kenya, Uganda, Tanzania — PVoC-type
Pre-export verification programmes operate in these markets for many product categories, with appointed inspection agencies. Scope by HS code changes, so confirm before production rather than before the vessel.
West Africa — national programmes
Several francophone and anglophone markets run their own verification-of-conformity schemes. Same rule: the certificate is obtained in China, on your product, against your invoice.
Algeria — Certificate of Conformity (COC)
Algeria requires a certificat de conformité for a wide range of imported goods, PVC floor coverings included. The certificate is issued by bodies accredited for the Algerian programme, against IANOR standards, before shipment — a request raised after the vessel sails arrives too late, and clearance at Algiers or Oran stalls with storage charges running. Confirm the HS code (PVC flooring sits under HS 3918) and the applicable standard with your clearing agent before production, not before loading.
The practical consequence
Add two to four weeks to your plan for conformity, and treat it as a production milestone, not an administrative afterthought. A container that sails without the certificate is not early — it is blocked.
Read the Nigeria file in detail — Form M, SONCAP, PAAR and who handles which — in sourcing into Nigeria.
2 · Used machinery: three checks that decide the outcome
Hours against wear
A hour meter can be replaced or reprogrammed. Wear on parts that age with use — undercarriage, pads, discs, blades — cannot be faked four times at once. Compare the number with the metal.
A load test, not idle running
The machine must work with real material during the visit, filmed. An idling engine video proves that the engine starts, nothing more.
Spare parts in your country
The cost that arrives after the purchase. Before negotiating price, ask for the main wear parts and the replenishment lead time. A model with no local support is a stationary asset.
The full checklist by equipment type is in the used-goods guide, and the freight side for heavy equipment is in our machines guide.
3 · Consolidation turns three small orders into one shipment
African buyers often buy several lines from different provinces. Shipping them separately means three bookings, three sets of documents and three clearance entries — and on small volumes, that is what makes a trial order uneconomic. Consolidating in Shanghai or Ningbo gives you one booking and one entry, but only if someone in China receives, checks and labels each supplier's goods before the container is stuffed.
That is also the moment to inspect: cartons counted against the packing list, part numbers verified carton by carton (the defect sampling never finds), and photographs of what actually went in.
4 · Lanes, ports and the cash cycle
- West Africa: Lagos (Apapa for general cargo, Tin Can for containers), Tema, Abidjan, Dakar, Douala, Cotonou.
- East and Southern Africa: Mombasa, Dar es Salaam, Durban, and Beira for some corridors.
- Transit: commonly 28–45 days from Chinese ports depending on the lane, plus clearance at destination, which on congested West African ports often runs longer than the quote suggests.
- Free time: ask for the destination free days in writing. A week either way moves the total cost more than the ocean freight difference you negotiated.
5 · Payment, honestly
Three rules: small deposit, balance after evidence, never the full amount to a stranger. Price in USD. If you buy in francophone West Africa, note that the CFA franc is pegged to the euro rather than floating freely — your exposure moves with EUR/USD, which is a different (and often more predictable) risk than a managed local currency.
We never hold the goods money. It goes from you to the supplier, directly, which is what allows us to write "do not pay" when the goods do not match. Details in the staged-payment rule.
6 · What we do, and what we do not
We do
Verify the supplier before your deposit; inspect before your balance (USD 60 for up to 90 minutes, video and written report; an AQL day for production lots); receive, check and consolidate multiple suppliers; prepare export documents that match the cargo; test a used machine under load, filmed.
We do not
Clear customs at destination, obtain SONCAP or PVoC certificates for you (we make sure the product data the agency needs is ready), hold your goods money, or promise a landed cost.
Price bands by inspection type: what inspections cost in China. French-language buyers: contrôler avant de payer · commission d'agence.
Common questions
What does Nigeria require before goods leave China?
For regulated products, SONCAP conformity must be completed before shipment, which typically takes two to four weeks. Without it the Pre-Arrival Assessment Report cannot be raised and the container sits at Apapa or Tin Can. Form M is opened through an authorised Nigerian bank and PAAR is raised by customs from your final invoice, packing list and bill of lading — all three depend on what is produced in China, so the paperwork should start the day the purchase order is signed.
Which African markets use pre-shipment conformity schemes?
Several do, under different names and scopes: Nigeria's SONCAP, PVoC-type programmes in Kenya, Uganda and Tanzania, Algeria's certificat de conformité, and national schemes in parts of West Africa. Scope depends on the product category and changes from time to time, so confirm with your clearing agent and the appointed inspection agency before production — not after the goods are packed.
Does Algeria require a COC for flooring imports?
Yes. Algeria runs a certificat de conformité programme covering a wide range of goods, PVC flooring included. The certificate must be issued before shipment by a body accredited for the Algerian programme, against IANOR standards. Without it the container clears slowly or not at all, and storage charges run from day one. Start the process when the purchase order is signed, not when the goods are packed.
How do I check a used machine before paying from Africa?
Three things on site: running hours cross-checked against wear on parts that age with use, a load test with real material rather than idle running, and spare-part availability for that specific model in your country. Add the serial number on video and documents that match the plate.
Is consolidation worth it for small African orders?
Usually yes. Several suppliers in different provinces can ship as one consignment from Shanghai or Ningbo — one booking, one set of export documents and one clearance entry instead of three. It requires someone in China to receive, check and label each supplier's goods before the container is stuffed.